Prior to construction:
September 11, 2022 Following the demolition of the portico:
October 6, 2022 Windscreens go up on the construction fence:
October 21, 2022 – Earth starting to get moved around:
November 4, 2022 – Forms being put together for the footers:
November 11, 2022 – Rebar support being installed in the footers:
November 18, 2022 – Concrete has been poured into the footers & the water trap has been put in:
December 2, 2022 – Crane day!
December 9, 2022 – Tennis Court removal.
December 16, 2022 – Ready for the concrete slab pour.
January 6, 2023 – Concrete slab pour complete. Curb pour & future parking lot island.
January 13,2023 – Parking lot islands going in. Also, new sidewalk coming into the building.
January 20, 2023 – Islands have been curbed. Sidewalks poured. New stairway up to 30A. Steel going vertical!